Thursday, March 15, 2007

Upcoming Seminar on Green Homes



Time is flying by with our homes just weeks away from being delivered, and yet somehow I convinced a few people that I know what I'm doing AND...they invited me to share this knowledge IN CHICAGO! So in a few weeks, I'll be making the trip north (and stopping by IKEA) to spread the gospel of EcoUrban - Green and Pre-Fabulous...

Pre-fab Green Homes
April 28, 2007
1:00 - 3:00 P.M.
Chicago Center for Green Technology
445 North Sacramento Boulevard

Sponsor: Chicago Center for Green Technology,
Free event. Registration required.

Presenter: Jay Swoboda, ecoUrban Homes

SYNOPSIS
Expressing one’s self through a custom-designed home is often beyond the financial reach of many buyers. This seminar will explain how modular and other styles of pre-fab construction can offer design and production technologies that have the potential to deliver affordable, high quality homes to EVERYONE. Finally, we will take a look at how market-forces are making green homes and green products make sense financially to both builders and homeowners.

Register by calling the hotline at 312/746.9642, or by emailing your desired class and contact information.

Monday, February 26, 2007

I can almost taste it...


Slow but ever so slowly I'm getting things worked out with Contempri Homes. I guess in this business once you are in line and make a change...you go to the END OF THE LINE. Still stuggling with doors and windows but everything else is ready to go. I will soon be placing orders for flooring, fixtures, appliances, etc. and with any luck we should have the unit delivered by the middle of April. In the meantime, lots of prep work for our other lots, but it is going smoothly. Website is really looking good and now I just need to get the details of our sales and marketing figured out. I can almost taste it...

Wednesday, January 10, 2007

Finally...my boots got dirty


Ground is all sorts of dug up, concrete and waterproofing are in place...just waiting on a confirmation from Contempri Homes for a delivery date - but I have to stop making changes to the design if I am to get this before March. I guess after waiting this long another month will only give me more time to get our sales package and marketing more developed.

Tuesday, December 12, 2006

Closing Time

Worked out the finer detail of our construction loan and with any luck we'll have some money in the bank after we empty our pockets one last time. I guess it feels good to know that we are really moving forward - without this loan commitment letter in hand it never felt right to break ground which we will be doing very soon on 3140 Pennsylvania. I've got the details worked out and 18 months later we are finally going build some homes.

Monday, November 06, 2006

Committment is Scary

I made the decision to have Contempri Homes build our first units. They were able to build a flat roof and they have Iceynene foam insulation at a reasonable price. I sent my deposit and we are off to the races. Changed around the bathroom on the second floor and have been fine tuning our design to meet the requirements of the LEED for Homes certification. Shooting for a early February 2007 delivery.

Monday, October 16, 2006

Dwell Conference

Just spent a few days getting inspired in San Francisco at the Dwell conference. What an inspiration to see so many committed individuals who are collectively moving things forward - pushing design and asking important questions about HOW and WHY our homes and businesses are built and what products and materials we put into them. Lots more to learn, but this was a great step forward.

Things to do:

Follow up with Breckenridge Homes
Call Joesph Tanney with Res4 Architecture
Work with Dwell editors on a design challenge for affordable infill.

Monday, August 14, 2006

I feel like I'm hibernating...

After pushing so hard to get these homes built over the summer it feels as if I'm just derailing everything, and putting it on hold for a few months. I find myself fine tuning design details, picking out appliances and fixtures - and I believe that the home that eventually gets constructed will be better for having had this time on ice.

Thursday, July 20, 2006

No sense in rushing

I figure even if I get things worked out with our modular builder I won't have a home until late August at BEST, and the last thing I want is a home that hits the market at the wrong time. So, we decided that it would be best to move forward with a February/March 2007 delivery to hit the market at the best time. This allows me lots of time to work out our construction loan, get our website functional and create a real demand for EcoUrban Homes. Wish me luck!

Thursday, June 15, 2006

Two more lots

Closed on 3103-3105 Magnolia today. Great location, but awkward parcel size. Our plan is to build two historic units to complement our modern display home on Pennsylvania.

Total parcel count = 15

Wednesday, June 14, 2006

Time to start making some tough choices

I imagine I could have built 10 of these homes with a hammer myself by now, but we are committed to the process and the building system approach. I am just amazed how clueless the front office of almos every modular builders I have attempted to work with are at moving custom designs from ideas on paper to homes on land. Advanced Building Concepts continues to work hard, but I'm not convinced they can even deliver and Contempri just won't get back to me. Am I missing something here?

Monday, May 15, 2006

Greening the Heartland

I presented a "poster" at the Greening the Heartland conference in Kansas City recently and was really encouraged by the reaction to our building plan and design. The conference wasn't overly technical and there was a lot of preaching to the choir, but I think most of left with some great distributor contacts and the knowledge that we are not alone in our effort to green up homes across America.

Sunday, April 02, 2006

Still Looking for Modular Builder...

Advanced Building Concepts just is unable to figure out a flat roof and they are really bad about communication. I've deceided to open up my call list again and Contempri Homes in Pinckneyville might just be getting a call.

Saturday, April 01, 2006

Land and more land...

EcoUrban closed a big parcel of land today located on the corner of Arsenal and Minnesota. We hope this will be the future of home of 10-12 new green homes and we hope to build on the momentum of the neighborhood with so many other projects in development.

Sunday, March 26, 2006

Green, Green and more Green

We have committed to the USGBC to build our homes under the LEED for Homes certification program and I attended the training in Grand Rapids, Michigan to register EcoUrban Homes as a builder in the pilot program. While I imagine I could have viewed the powerpoint presentation from St. Louis it was worthwhile to explore a new city and share with the other 15 or so attendees the spirit of green building. More details later.

Wednesday, March 15, 2006

Stopped in Action

I guess according to my original timeline I should be delivering the first modules today on their foundations. However, the reality is that modular manufacturers just don't get it - and we are heading to Linton, Indiana tomorrow to "tour" Advance Building Concepts factory and hopefully kiss enough ass for them to finally get them to committ to building our homes.

We selected a General Contractor back in February (or I should say they selected us as the only contractor to submit a bid) and we have been adjusting our design and floor plans ever since to hit our $100/sq. ft. target. Right now we are at $180/ft.

I'm not sure what else I can be in action on. I've pulled together the land for up to 12 homes to be built at a cost of around $125K after some unexpected commissions - and am working on an additional 4 lots that would come with some unwanted buildings. The architect seems to be pushing our project around meetings that are spaced out by days and weeks at times and I still don't have a firm grasp on when I should (if at all) pull the trigger.

I know that there is more to be done (Public Service Commission Issues, tax issues, LRA issues, marketing, etc.) but I just feel stopped in action. Perhaps after this weekend in New Orleans I'll find some new inspiration.

Monday, January 16, 2006

Bad News Comes in Pairs

We were just a few days from putting the seal on the construction drawings when we got two days of bad news. First our prospective modular manufacturer got a big order from Jefferson Parish, Louisiana and pushed off our timeline by two months. Then our regional sewer district passed regulations prohibiting bathrooms in basements without proper pumps to get water and sewage up to a newly required 1st floor waste lateral. Just another day trying to build modular.

Wednesday, November 09, 2005

Construction Timeline

Depending on how our land acquisition goes this next month, I would like to work out a plan to get our construction documents to the manufacturer by January 15, 2006, with hopes of getting our prototype on foundation by March 15th.

Tuesday, November 08, 2005

Marine Villa Environment

E-mail from Craig Schmid on 11/8/05:

Basically, we are looking for excellent quality housing (mostly rehab), single-family detached homes (unless converting four families to two families), homeowner occupied, three-sides of brick with masonry rear, basement, compatible with the historic architecture (no modernism, cubism, etc.), meeting the urban model of garages in rear, and selling for a minimum price range of $150,000 to $200,000.

In the 20th Ward (other than in Benton Park West) you should be talking with Sam Green, CDA housing analyst, at (314) 622-3400 (ext. 232) or greens@stlouiscity.com. Sam and JoAnn work very well together.

Thanks.

Craig Schmid

Thursday, November 03, 2005

Infill Development Details


Who are the Buyer’s:
College educated couples (married, unmarried living together) transitioning from first or second jobs out of college into a more permanent position or having successfully launched their own business. Also, could be an empty-nester couple looking for good city living or divorced professional looking to start over. Emphasis on young architects and design professionals. The big issue is someone who wants a yard and doesn’t want a condo fee and likes the idea of working in a community garden and volunteering at the senior center across the street.

Price Range:
$169900 @ 1258 sq. feet without a garage and $189900 with garage and $189900 @ 1440 sq. feet (involves stretching house approx. 6 more feet) without a garage and $209,900 with garage. We would like to push this upward by at least $10,000 through our marketing and promotion of the area, which will not only get everyone on our side in the neighborhood but will lead prospective homeowners to our development(s) by directing a significant portion of our efforts to pumping up Benton Park West.

Size of Home:
1258 up to 1440 square feet

Check out http://www.mayorslay.com/polls/090805squarefeetresults.asp which provides data on a group of participants who responded to a survery about home size and city living.

Friday, October 21, 2005

Neighborhood Preservation Tax Credit

Neighborhood Preservation Act

The deadline for the 2006 tax credit application will be November 18, 2005.

This act authorizes state tax credits for residential rehabilitation and construction costs for properties located in distressed communities* or defined census blocks.

Purpose

To provide an incentive for the rehabilitation or construction of owner-occupied homes in certain areas of the state.

Authorization
Sections 135.475 to 135.487, RSMo

How The Program Works

The Department of Economic Development (DED) issues state tax credits to a homeowner who rehabilitates a home or to a homeowner or developer that constructs a new home for owner-occupancy in certain areas of the state.

Eligible Areas

“Qualifying areas,” include “distressed communities,” as defined in 135.530, RSMo, and areas with a median household income of less than 70% of the median household income for the applicable MSA or non-MSA. “Eligible areas,” with a median household income of 70% to 89% of the median household income for the applicable MSA or non-MSA.

NEW CONSTRUCTION

Eligible Area

For new construction in the state of Missouri under this category, the following must apply:


The newly constructed residence must be replacing a residence that is equal to or more than forty years of age and is demolished for the purposes of constructing a replacement residence.

The residence is constructed on vacant property, which has been classified (for tax purposes) for not less than forty continuous years as residential, utility, commercial, railroad, or other real property.

If in a metropolitan statistical area or non-metropolitan statistical area, the property must be in a United States census block group which has a median household income of less than ninety percent (90%) but greater than or equal to seventy percent (70%) of the median household income for the metropolitan statistical area in which the census block group is located.

There is no minimum cost that you must incur for new construction. The maximum tax credit amount is $25,000 in any 10-year period. For example, if you spend $25,000 to construct your home, you could receive a $3,750 tax credit [$25,000 x 15% = $3,750]. NOTE: (You may be eligible to reapply continuously until you reach the $25,000 maximum tax credit amount if your “new construction” has not been completed and you have incurred additional construction expenses.)

Qualifying (Distressed Community) Area

If doing new construction in the state of Missouri under this category, the following must apply:

The land must have been vacant for at least two years and is or was occupied by a structure condemned by the local entity.

If in a metropolitan statistical area or non-metropolitan statistical area, the property must be in a United States census block group, which has a median household income of less than seventy percent (70%).